Red Hook Recreation Area Track 1, Soccer Fields 3-5, and Ballfields 1-4 Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the track & field and convert three soccer fields and four ballfields from natural turf to synthetic turf at Red Hook Recreation Area.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: November 2017
Projected Completion Date: March 2019
Completion Date: April 2019

Procurement

Start Date: April 2019
Projected Completion Date: January 2020
Adjusted Completion Date: April 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

Red Hook Recreation Area , Brooklyn
Columbia Street and Bay Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 02/20/2020