Red Hook Recreation Area Track 1, Soccer Fields 3-5, and Ballfields 1-4 Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    4% complete

This project will reconstruct the track & field and convert three soccer fields and four ballfields from natural turf to synthetic turf at Red Hook Recreation Area.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: November 2017
Projected Completion Date: March 2019
Completion Date: April 2019

Procurement

Start Date: April 2019
Projected Completion Date: January 2020
Completion Date: March 2021

Construction

Start Date: July 2021
Projected Completion Date: January 2023

Understand how we build parks.

Funding

Total Funding: $61,940,000
Funding Source: Mayoral

Location

Red Hook Recreation Area , Brooklyn
Columbia Street and Bay Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/29/2021

Was this information helpful?