Echo Park Playground and Basketball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the playground, spray shower, and basketball courts at Richman (Echo) Park.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: December 2016
Projected Completion Date: December 2017
Completion Date: September 2018

Procurement

Start Date: September 2018
Projected Completion Date: June 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Richman (Echo) Park , Bronx
Valentine Avenue between East Tremont and East Burnside Avenues

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 10/18/2018