Staten Island Street Tree Planting FY17

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    69% complete

This project will plant new street trees throughout Staten Island.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: June 2016
Projected Completion Date: June 2016
Completion Date: July 2016

Procurement

Start Date: July 2016
Projected Completion Date: April 2017
Completion Date: May 2017

Construction

Start Date: May 2017
Projected Completion Date: November 2018

Understand how we build parks.

Funding

Total Funding: $1,375,000
Funding Sources:
  • Mayoral
  • Private

Location

Various locations, Staten Island.

Project Staff

Contact NYC Parks about this project

Last updated: 05/21/2018