Queens Street Tree Planting FY17 - Community Boards 6,9,10

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    92% complete

This project will plant new trees in community boards 6,9,10 in Queens.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: June 2016
Projected Completion Date: June 2016
Completion Date: July 2016

Procurement

Start Date: July 2016
Projected Completion Date: April 2017
Completion Date: March 2017

Construction

Start Date: April 2017
Projected Completion Date: October 2018

Understand how we build parks.

Funding

Total Funding: $1,500,000
Funding Sources:
  • Mayoral
  • City Council
  • Private

Location

Various locations, in Queens community boards 6,9,10.

Project Staff

Contact NYC Parks about this project

Last updated: 05/24/2018