Brooklyn Street Tree Planting FY17 - Community Boards 11,13,15

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new trees in Community Boards 11, 13, and 15 in Brooklyn.

Project Timeline

Design

Start Date: June 2016
Projected Completion Date: June 2016
Completion Date: July 2016

Procurement

Start Date: July 2016
Projected Completion Date: April 2017
Completion Date: March 2017

Construction

Start Date: April 2017
Projected Completion Date: September 2018
Completion Date: August 2018

Understand how we build parks.

Funding

Total Funding: $2,373,000
Funding Sources:
  • Mayoral
  • City Council
  • Private

Location

Various locations in Brooklyn

Project Staff

Contact NYC Parks about this project

Last updated: 10/15/2018