Brooklyn Street Tree Planting FY17 - Community Boards 8,9,17

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    96% complete

This project will plant new trees in community boards 8,9,17 in Brooklyn.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: June 2016
Projected Completion Date: June 2016
Completion Date: July 2016

Procurement

Start Date: July 2016
Projected Completion Date: April 2017
Completion Date: April 2017

Construction

Start Date: April 2017
Projected Completion Date: October 2018

Understand how we build parks.

Funding

Total Funding: $1,600,000