Red Hook Recreation Area Ballfield 9 and Soccer Field 2 Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    59% complete

This project will convert a ballfield and soccer field from natural turf to synthetic turf and remediate contaminated soils at Red Hook Recreation Area.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: February 2018
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: March 2019
Completion Date: June 2019

Construction

Start Date: September 2019
Projected Completion Date: March 2021
Adjusted Completion Date: June 2022

Understand how we build parks.

Funding

Total Funding: $23,597,000
Funding Source: Mayoral

Location

Red Hook Recreation Area , Brooklyn
Clinton Street between Bay Street and Halleck Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/04/2022

Was this information helpful?