Red Hook Recreation Area Ballfield 9 and Soccer Field 2 Reconstruction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will convert a ballfield and soccer field from natural turf to synthetic turf and remediate contaminated soils at Red Hook Recreation Area.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: February 2018
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: March 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

Red Hook Recreation Area , Brooklyn
Located on Clinton Street between Bay and Halleck Streets

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 12/12/2018