Red Hook Recreation Area Ballfield 9 and Soccer Field 2 Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    2% complete

This project will convert a ballfield and soccer field from natural turf to synthetic turf and remediate contaminated soils at Red Hook Recreation Area.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: February 2018
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: March 2019
Completion Date: June 2019

Construction

Start Date: September 2019
Projected Completion Date: March 2021

Understand how we build parks.

Funding

Total Funding: $20,296,000
Funding Source: Mayoral

Location

Red Hook Recreation Area , Brooklyn
Clinton Street between Bay Street and Halleck Street

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/18/2019