McCarren Park Bathhouse Roof & Exterior Walls Reconstruction
-
100% complete
-
100% complete
-
0% complete
This project will reconstruct the roof and exterior masonry walls at the McCarren Park Bathhouse.
Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.
Project Timeline
Design
Start Date: June 2016
Projected Completion Date:
September 2017
Completion Date:
January 2020
Procurement
Start Date: January 2020
Projected Completion Date:
October 2020
Completion
Date:
November 2021
Construction
Start Date: April 2022
Projected Completion Date:
October 2024
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
McCarren Park
, Brooklyn
Lorimer Street between Bayard Street and Driggs Avenue
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 05/17/2022