McCarren Park Pool Bathhouse Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the roof, exterior masonry walls and foundation walls at the McCarren Park Pool Bathhouse.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: June 2016
Projected Completion Date: September 2017
Completion Date: January 2020

Procurement

Start Date: January 2020
Projected Completion Date: October 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

McCarren Park , Brooklyn
Lorimer Street between Bayard Street and Driggs Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 02/27/2020