McCarren Park Bathhouse Roof & Exterior Walls Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the roof and exterior masonry walls at the McCarren Park Bathhouse.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: June 2016
Projected Completion Date: September 2017
Completion Date: January 2020

Procurement

Start Date: January 2020
Projected Completion Date: October 2020
Completion Date: November 2021

Construction

Start Date: April 2022
Projected Completion Date: October 2024

Understand how we build parks.

Funding

Total Funding: $11,665,000
Funding Source: Mayoral

Location

McCarren Park , Brooklyn
Lorimer Street between Bayard Street and Driggs Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 05/17/2022