McCarren Park Pool Bathhouse Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the roof, exterior masonry walls and foundation walls at the McCarren Park Pool Bathhouse.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: June 2016
Projected Completion Date: September 2017
Completion Date: November 2017

Procurement

Start Date: November 2017
Projected Completion Date: August 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

McCarren Park , Brooklyn
Located on East Of Lorimer Street Between Bayard Street & Driggs Avenue In McCarren Park, Borough of Brooklyn.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 08/17/2018