Queens General Site Work (QG-1316M)
-
100% complete
-
100% complete
-
100% complete
This project will construct new fitness equipment at Alley Pond Park and Alley Athletic Playground, reconstruct the seating area at One Room Schoolhouse Park, and construct a new meditation garden at Kissena Corridor Park.
Project Timeline
Design
Start Date: May 2016
Projected Completion Date:
May 2017
Completion Date:
August 2017
Procurement
Start Date: August 2017
Projected Completion Date:
April 2018
Completion
Date:
May 2018
Construction
Start Date: October 2018
Projected Completion Date:
December 2019
Completion
Date:
December 2019
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Locations
-
Alley Athletic Playground, Queens
Grand Central Parkway, Union Turnpike, Winchester Boulevard -
Alley Pond Park, Queens
Springfield Boulevard / 73rd Avenue / 76th Avenue to Tree Line & Natural Area -
Kissena Corridor Park, Queens
Lawrence Street, North Hempstead Turnpike, Elder Avenue, Kissena Boulevard -
One Room Schoolhouse Park, Queens
Astoria Boulevard, 90 Street
Project Staff
Project Liaison: Mike Dockett
Contact NYC Parks
about this project
Last updated: 08/15/2022