Queens General Site Work (QG-1316M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will construct new fitness equipment at Alley Pond Park, reconstruct the seating area at One Room Schoolhouse Park, and construct a new meditation garden at Kissena Corridor Park.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: May 2016
Projected Completion Date: May 2017
Completion Date: August 2017

Procurement

Start Date: August 2017
Projected Completion Date: April 2018
Completion Date: May 2018

Construction

Start Date: October 2018
Projected Completion Date: December 2019

Understand how we build parks.

Funding

Total Funding: $1,556,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Locations

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 07/13/2018