Queens General Site Work (QG-1216M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    83% complete

This project will reconstruct a stairway at Cunningham Park, the passive area of Brinkerhoff Mall, and fencing around the dog run in Forest Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: May 2016
Projected Completion Date: May 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018
Completion Date: March 2018

Construction

Start Date: March 2018
Projected Completion Date: September 2019

Understand how we build parks.

Funding

Total Funding: $774,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Locations

  • Brinkerhoff Mall , Queens
    Brinkerhoff Avenue, Merrick Boulevard, 110 Road
  • Broad Channel Park , Queens
    Cross Bay Boulevard, East 16 to East 18 Roads, Channel Road
  • Cunningham Park , Queens
    Ballfields and Tennis Courts South of Union Turnpike between Francis Lewis Boulevard & 193rd Street
  • Forest Park , Queens
    (South) Park Lane South to North of Tennis Courts
 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 11/16/2018