Bronx, Manhattan and Queens Sandy-Related and Risk Management Tree Removal

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    87% complete

This project will remove Hurricane Sandy-damaged trees in the Bronx, Manhattan and Queens.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: May 2016
Projected Completion Date: June 2016
Completion Date: November 2016

Procurement

Start Date: November 2016
Projected Completion Date: July 2017
Completion Date: June 2017

Construction

Start Date: September 2017
Projected Completion Date: September 2018

Understand how we build parks.

Funding

Total Funding: $500,000
Funding Sources:
  • Mayoral
  • Federal

Location

Various locations, the Bronx, Manhattan and Queens.

Project Staff

Contact NYC Parks about this project

Last updated: 08/15/2018