Dutch Kills Playground Comfort Station Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the comfort station at Dutch Kills Playground.
Project Timeline
Design
Start Date: April 2016
Projected Completion Date:
April 2017
Completion Date:
May 2017
Procurement
Start Date: May 2017
Projected Completion Date:
January 2018
Completion
Date:
May 2018
Construction
Start Date: July 2018
Projected Completion Date:
January 2020
Completion
Date:
December 2019
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Dutch Kills Playground
, Queens
Crescent Street, 28th Street, 36th Avenue, 37th Avenue
Project Staff
Project Liaison: Joanne Amagrande
Contact NYC Parks
about this project
Last updated: 04/21/2021