Dutch Kills Playground and Court Area Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    12% complete

This project will reconstruct the playground and court area in Dutch Kills Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018
Completion Date: April 2018

Construction

Start Date: May 2018
Projected Completion Date: May 2019

Understand how we build parks.

Funding

Total Funding: $3,044,000
Funding Sources:
  • Mayoral
  • City Council

Location

Dutch Kills Playground , Queens
Crescent and 28th streets between 36th and 37th avenue in the Borough of Queens,

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 08/20/2018