Chelsea Green Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    25% complete

This project will construct a new park, including play equipment, seating, lighting, plantings, and other site furnishings at Chelsea Green.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: April 2016
Projected Completion Date: July 2017
Completion Date: July 2017

Procurement

Start Date: July 2017
Projected Completion Date: April 2018
Completion Date: March 2018

Construction

Start Date: July 2018
Projected Completion Date: July 2019

Understand how we build parks.

Funding

Total Funding: $2,588,000
Funding Sources:
  • Mayoral
  • City Council
  • Private

Location

Chelsea Green , Manhattan
West 20th Street between 6th and 7th Avenues

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 12/13/2018