Ferry Point Park Golf Course Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a golf course at Ferry Point Park.

Project Timeline

Design

Start Date: June 2008
Projected Completion Date: March 2009
Completion Date: March 2009

Procurement

Start Date: March 2009
Projected Completion Date: December 2009
Completion Date: September 2009

Construction

Start Date: October 2009
Projected Completion Date: November 2011
Completion Date: June 2014

Understand how we build parks.

Funding

Total Funding: $123,000,000

Location

Ferry Point Park, Bronx
Balcom Avenue, Schley Avenue, Miles Avenue, Emerson Avenue, Bronx-Whitestone Bridge

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/20/2017