Levy Playground, McDonald Park and DeMatti Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    69% complete

This project will reconstruct three comfort stations at various locations in Staten Island.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: February 2015
Projected Completion Date: February 2016
Completion Date: July 2016

Procurement

Start Date: July 2016
Projected Completion Date: April 2017
Completion Date: June 2017

Construction

Start Date: July 2017
Projected Completion Date: October 2018
Adjusted Completion Date: January 2019

Understand how we build parks.

Funding

Total Funding: $6,930,000
Funding Source: Mayoral

Locations

 

Project Staff

Project Liaison: Charles Fall
Contact NYC Parks about this project

Last updated: 12/15/2018