Levy Playground, McDonald Park and DeMatti Playground Comfort Station Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    15% complete

This project will reconstruct three comfort stations at various locations in Staten Island.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: February 2015
Projected Completion Date: February 2016
Completion Date: July 2016

Procurement

Start Date: July 2016
Projected Completion Date: April 2017
Completion Date: June 2017

Construction

Start Date: July 2017
Projected Completion Date: October 2018

Understand how we build parks.

Funding

Total Funding: $6,930,000
Funding Source: Mayoral