Lyons Recreation Center Reconstruction
-
100% complete
-
60% complete
-
0% complete
This project will partially reconstruct Lyons Pool Recreation Center in Staten Island.
Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.
Project Timeline
Design
Start Date: January 2016
Projected Completion Date:
October 2016
Completion Date:
March 2019
Procurement
Start Date: March 2019
Projected Completion Date:
December 2019
Adjusted Completion
Date:
June 2022
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Lyons Pool
, Staten Island
Victory Boulevard and Murray Hulbert Avenue
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 06/24/2022