Project Timeline
Design
Start Date: March 2014
Projected Completion Date:
February 2016
Completion Date:
April 2016
Procurement
Start Date: April 2016
Projected Completion Date:
January 2017
Completion
Date:
January 2017
Construction
Start Date: March 2017
Projected Completion Date:
March 2018
Completion
Date:
September 2017