NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Martin Luther King Jr. Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    79% complete

This project will reconstruct Martin Luther King Jr. playground with new play equipment, a spray shower, synthetic turf area, basketball courts, lighting, fencing, pavements, plantings and site furnishings.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: January 2015
Projected Completion Date: December 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: August 2016

Construction

Start Date: September 2016
Projected Completion Date: December 2017

Understand how we build parks.

Funding

Total Funding: $3,802,000
Funding Source: Mayoral

Location

Martin Luther King Jr. Park, Manhattan
Malcolm X Boulevard (Lenox Avenue) Between West 113 and West 114 Streets, borough of Manhattan.

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/20/2017

Was this information helpful?