Queens Greenstreets and Green Infrastructure Construction Phase 3

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will construct green infrastructure to capture storm water at Greenstreets in Kew Gardens, Forest Hills and Corona in Queens.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: November 2015
Projected Completion Date: February 2016
Completion Date: September 2017

Procurement

Start Date: September 2017
Projected Completion Date: June 2018
Adjusted Completion Date: April 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

81st & 82nd Aves, Austin St, Queens & Yellowstone Blvds, Saunders St, 110th-113th Sts, 102nd St, 60th Ave, Calloway St, Horace Harding Expwy, Corona Ave, Booth St, Van Cleef St, Lewis Av, Eliot Ave

Project Staff

Contact NYC Parks about this project

Last updated: 01/22/2019