Lasker Pool and Rink Facility Reconstruction

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will reconstruct the Lasker Pool and Rink Facility in Central Park.

Project Update: All contract documents are now in final review to complete the design process.

Project Timeline

Design

Start Date: May 2016
Projected Completion Date: June 2017
Adjusted Completion Date: September 2017

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Location

Central Park, Manhattan
Central Park, between West 106th and West 108th Streets, Manhattan

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/16/2017