Louis C. Moser Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    84% complete

This project will reconstruct the playground at Louis C. Moser Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: December 2015
Projected Completion Date: October 2016
Completion Date: October 2016

Procurement

Start Date: October 2016
Projected Completion Date: July 2017
Completion Date: May 2017

Construction

Start Date: September 2017
Projected Completion Date: September 2018

Understand how we build parks.

Funding

Total Funding: $1,698,000
Funding Sources:
  • Mayoral
  • City Council

Location

Louis C. Moser Playground , Queens
77th Street and 25th Avenue

 