Stockton Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct new play equipment, including a spray shower, synthetic turf field and painted track; lighting; fencing; pavement; planting and site furnishings at Stockton Playground.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: January 2015
Projected Completion Date: December 2015
Completion Date: May 2016

Procurement

Start Date: May 2016
Projected Completion Date: February 2017
Completion Date: February 2017

Construction

Start Date: March 2017
Projected Completion Date: March 2018
Completion Date: April 2018

Understand how we build parks.

Funding

Total Funding: $3,712,000
Funding Source: Mayoral

Location

Stockton Playground , Brooklyn
662 Park Avenue, Brooklyn, NY 11206

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/16/2018