Stockton Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Stockton Playground with new play equipment, a spray shower, a synthetic turf field and painted track, lighting, fencing, pavement, plantings, and site furnishings.

Project Timeline

Design

Start Date: January 2015
Projected Completion Date: December 2015
Completion Date: May 2016

Procurement

Start Date: May 2016
Projected Completion Date: February 2017
Completion Date: February 2017

Construction

Start Date: March 2017
Projected Completion Date: March 2018
Completion Date: April 2018

Understand how we build parks.

Funding

Total Funding: $3,712,000
Funding Source: Mayoral

Location

Stockton Playground , Brooklyn
Park Avenue and Martin Luther King Jr. Place between Marcy Avenue and Tompkins Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 01/23/2019