Ten Eyck Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct new play equipment, including a spray shower, a synthetic turf field, a painted track, and a basketball court; lighting; fencing; pavement; planting and site furnishings at Ten Eyck Playground.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: January 2015
Projected Completion Date: December 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: February 2017

Construction

Start Date: March 2017
Projected Completion Date: March 2018
Completion Date: April 2018

Understand how we build parks.

Funding

Total Funding: $3,696,000
Funding Source: Mayoral

Location

Ten Eyck Playground , Brooklyn
242 Scholes Street, Brooklyn, NY 11206

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 08/17/2018