Little Claremont Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    59% complete

This project will reconstruct Little Claremont Playground.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: January 2015
Projected Completion Date: December 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: April 2017

Construction

Start Date: April 2017
Projected Completion Date: April 2018
Adjusted Completion Date: July 2018

Understand how we build parks.

Funding

Total Funding: $3,331,000
Funding Source: Mayoral

Location

Little Claremont Playgound , Bronx
Park Avenue and Claremont Parkway

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 07/16/2018