NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

Lyons Square Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    74% complete

This project will reconstruct Lyons Square Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: January 2015
Projected Completion Date: December 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: July 2016

Construction

Start Date: September 2016
Projected Completion Date: December 2017

Understand how we build parks.

Funding

Total Funding: $4,469,000
Funding Source: Mayoral

Location

Lyons Square Park, Bronx
Lyons Square Playground, located between Bruckner Boulevard, Bryant Avenue, Aldus Street, and Longfellow Avenue.

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/20/2017

Was this information helpful?