Longfellow Gardens Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Longfellow Gardens, including new play equipment, spray shower, seating, lighting, fencing, pavements and planting.

Project Timeline

Design

Start Date: January 2015
Projected Completion Date: December 2015
Completion Date: August 2016

Procurement

Start Date: August 2016
Projected Completion Date: May 2017
Completion Date: October 2017

Construction

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: September 2018

Understand how we build parks.

Funding

Total Funding: $2,506,000
Funding Source: Mayoral

Location

Longfellow Playground , Bronx
Longfellow Avenue, Lowell Street, East 165th Street

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 06/20/2021