Carl Schurz Park Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    4% complete

This project will reconstruct the children's playground in Carl Schurz Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: July 2017
Projected Completion Date: June 2018
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: May 2019
Completion Date: May 2019

Construction

Start Date: September 2019
Projected Completion Date: September 2020

Understand how we build parks.

Funding

Total Funding: $3,359,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Carl Schurz Park , Manhattan
East End Avenue from Gracie Square to East 86th Street

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 12/12/2019