Astoria Park Sewer Installation

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will construct a sanitary sewer to serve the North Playground comfort station and the Astoria Pool concession in Astoria Park.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline


Start Date: June 2016
Projected Completion Date: June 2017
Completion Date: August 2017


Start Date: August 2017
Projected Completion Date: May 2018


The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.


Total Funding: Less than $1 million
Funding Source: Mayoral


Astoria Park , Queens
Located off of Shore Boulevard between 23rd Terrace and 23rd Drive