Overlook Park Seating Area Reconstruction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will reconstruct the seating area, paths, and plantings at Overlook Park.

Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: October 2017
Completion Date: November 2017

Procurement

Start Date: November 2017
Projected Completion Date: August 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Mayoral

Location

Overlook Park , Queens
Ditmars Boulevard, 98th Street, 99th Street, 22nd Drive

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project