Queens Roller Hockey Rinks Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct roller hockey rinks at Juniper Valley Park, Harvey Park, Mafera Park and College Point Park.

Project Timeline

Design

Start Date: October 2015
Projected Completion Date: October 2016
Completion Date: December 2016

Procurement

Start Date: December 2016
Projected Completion Date: September 2017
Completion Date: September 2017

Construction

Start Date: February 2018
Projected Completion Date: February 2019
Completion Date: November 2018

Understand how we build parks.

Funding

Total Funding: $1,509,000
Funding Sources:
  • Mayoral
  • City Council

Locations

  • College Point Fields , Queens
    130th Street & 23rd Avenue
  • Harvey Park , Queens
    15 to 20 Avenues, East of Whitestone Expressway
  • Juniper Valley Park , Queens
    Dry Harbor Road, 80th Street, Juniper Boulevard North, Juniper Boulevard South, Lutheran Avenue
  • Mafera Park , Queens
    65 Place & Catalpa Avenue & 68 Avenue
 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 12/15/2018