  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    74% complete

This project will reconstruct and provide for the adaptive re-use of the Reflecting Pool in Flushing Meadows Corona Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: August 2016
Projected Completion Date: July 2017
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: September 2018
Completion Date: May 2019

Construction

Start Date: September 2019
Projected Completion Date: September 2020
Adjusted Completion Date: November 2020

Understand how we build parks.

Funding

Total Funding: $6,857,000
Funding Source: Mayoral

Location

Flushing Meadows Corona Park , Queens
Between Unisphere and Fountain of the Planets

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project