Belt Parkway Tree Planting and Ecological Restoration

  • Design
    80% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will plant trees within the Belt Parkway right-of-way. It will also restore natural areas adjacent to the Parkway.

Project Update: The design completion date has changed. Some of the common reasons why a completion date has changed are: scope and funding are added to a project, design changes due to comments from other government agencies and the public, design changes due to field conditions found during site testing and/or issues with a design consultant.

Project Timeline

Design

Start Date: July 2018
Projected Completion Date: January 2020
Adjusted Completion Date: March 2021

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Greater than $10 million
Funding Source: Mayoral

Locations

 

Project Staff

Contact NYC Parks about this project

Last updated: 11/19/2020