Highland Park Lower Western Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    60% complete

This project will reconstruct Lower Western Playground in Highland Park.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018
Completion Date: April 2018

Construction

Start Date: July 2018
Projected Completion Date: July 2019
Adjusted Completion Date: October 2019

Understand how we build parks.

Funding

Total Funding: $2,619,000
Funding Sources:
  • Mayoral
  • City Council

Location

Highland Park , Queens
Jamaica Avenue Between Elton Street and Cleveland Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 09/13/2019