Highland Park Lower Western Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    76% complete

This project will reconstruct Lower Western Playground in Highland Park.

Due to COVID related construction industry impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018
Completion Date: April 2018

Construction

Start Date: July 2018
Projected Completion Date: July 2019
Adjusted Completion Date: April 2020

Understand how we build parks.

Funding

Total Funding: $2,619,000
Funding Sources:
  • Mayoral
  • City Council

Location

Highland Park , Queens
Jamaica Avenue Between Elton Street and Cleveland Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 05/22/2020