Highland Park Lower Western Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the Western Lower Highland Playground to include play equipment and seating areas.

Project Update: A date has been set for construction to begin.

Project Timeline

Design

Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: May 2017

Procurement

Start Date: May 2017
Projected Completion Date: February 2018
Completion Date: April 2018

Construction

Start Date: July 2018
Projected Completion Date: July 2019

Understand how we build parks.

Funding

Total Funding: $2,176,000
Funding Sources:
  • Mayoral
  • City Council

Location

Highland Park , Queens
Playground West of the Comfort Station in Lower Highland Park on Jamaica Avenue Between Elton and Cleveland Streets

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 08/20/2018