Bronx River (Shoelace) Park Link Reconstruction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct paths and drainage systems, construct new entrances, and bioswales and rain gardens, and formalize the Bronx River Greenway in Shoelace Park.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Start Date: November 2016
Projected Completion Date: October 2017
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Borough President
  • City Council
  • Federal

Location

Bronx River Parkway , Bronx
Bronx Boulevard between 212th Street and 229th Street.

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 11/14/2018