Rudd Playground Skate Park and Basketball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    64% complete

This project will reconstruct the basketball courts and construct a new skate park at Rudd Playground including a new accessible ramp to connect the two levels within the park and reconstruction of pavements, stairs, fencing, benches, plantings, drainage and water supply systems, and park security lighting.

Due to COVID related construction industry impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: September 2017
Completion Date: February 2018

Procurement

Start Date: February 2018
Projected Completion Date: November 2018
Completion Date: June 2019

Construction

Start Date: July 2019
Projected Completion Date: July 2020

Understand how we build parks.

Funding

Total Funding: $2,983,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Rudd Playground , Brooklyn
Aberdeen Street east of Bushwick Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 06/02/2020