Rudd Playground Skate Park and Basketball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct basketball courts and construct a new skate park at Rudd Playground. Site amenities will include new pavements, a new accessible ramp to connect the two levels within the park, reconstruction of stairs, fencing, benches, plantings, drainage and water supply systems and park security lighting.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: September 2017
Completion Date: February 2018

Procurement

Start Date: February 2018
Projected Completion Date: November 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • City Council

Location

Rudd Playground , Brooklyn
Park is located on Aberdeen Street, just east of Bushwick Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 08/20/2018