Rudd Playground Skate Park and Basketball Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    96% complete

This project will reconstruct the basketball courts and construct a new skate park at Rudd Playground including a new accessible ramp to connect the two levels within the park and reconstruction of pavements, stairs, fencing, benches, plantings, drainage and water supply systems, and park security lighting.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: October 2016
Projected Completion Date: September 2017
Completion Date: February 2018

Procurement

Start Date: February 2018
Projected Completion Date: November 2018
Completion Date: June 2019

Construction

Start Date: July 2019
Projected Completion Date: July 2020
Adjusted Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $2,983,000
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

Rudd Playground , Brooklyn
Aberdeen Street east of Bushwick Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/29/2020