NYC Resources311Office of the Mayor

Official Website of the New York City Department of Parks & Recreation

City Line Park Synthetic Turf Construction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will convert the existing asphalt athletic field into a multipurpose active recreation area to include a synthetic turf field, skate park, basketball court, adult fitness equipment and other site amenities.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: June 2016
Projected Completion Date: June 2017
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

City Line Park, Brooklyn
Fountain Avenue, Welden Street, McKinley Avenue.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 02/16/2018

Was this information helpful?