Spring Creek Greenstreets and Green Infrastructure Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    10% complete

This project will construct green infrastructure to capture storm water at Greenstreets near Spring Creek in Queens.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: June 2016
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019
Completion Date: June 2019

Construction

Start Date: August 2019
Projected Completion Date: February 2020

Understand how we build parks.

Funding

Total Funding: $3,090,000
Funding Source: Federal

Location

Spring Creek Park Addition , Queens
Belt Parkway between Erskine Street and Cross Bay Boulevard, and 157th Avenue between 78th and 79th Streets.

 

Project Staff

Contact NYC Parks about this project

Last updated: 12/12/2019