Spring Creek Greenstreets and Green Infrastructure Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    47% complete

This project will construct green infrastructure to capture storm water at Greenstreets near Spring Creek in Queens.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: June 2016
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019
Completion Date: June 2019

Construction

Start Date: August 2019
Projected Completion Date: February 2020
Adjusted Completion Date: June 2020

Understand how we build parks.

Funding

Total Funding: $3,090,000
Funding Source: Federal

Location

Spring Creek Park Addition , Queens
Belt Parkway between Erskine Street and Cross Bay Boulevard, and 157th Avenue between 78th and 79th Streets.

 

Project Staff

Contact NYC Parks about this project

Last updated: 03/31/2020