Spring Creek Greenstreets and Green Infrastructure Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct green infrastructure to capture storm water at Greenstreets near Spring Creek in Queens.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: September 2015
Projected Completion Date:
June 2016
Completion Date:
July 2018
Procurement
Start Date: July 2018
Projected Completion Date:
April 2019
Completion
Date:
June 2019
Construction
Start Date: August 2019
Projected Completion Date:
February 2020
Completion
Date:
November 2020
Understand how we build parks.
Funding
Funding Source: Federal
Location
Spring Creek Park Addition
, Queens
Belt Parkway between Erskine Street and Cross Bay Boulevard, and 157th Avenue between 78th and 79th Streets.
Project Staff
Contact NYC Parks about this projectLast updated: 01/15/2021