Spring Creek Greenstreets and Green Infrastructure Construction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will construct green infrastructure to capture storm water at Greenstreets near Spring Creek in Queens.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: June 2016
Completion Date: July 2018

Procurement

Start Date: July 2018
Projected Completion Date: April 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Federal

Location

Spring Creek Park Addition , Queens
Belt Parkway between Erskine Street and Cross Bay Boulevard, and 157th Avenue between 78th and 79th Streets.

 

Project Staff

Contact NYC Parks about this project

Last updated: 11/16/2018