Pelham Bay Park Natural Shoreline Reconstruction

  • Design
    100% complete
  • Procurement
    85% complete
  • Construction
    0% complete

This project will remove intrusive infrastructure from the natural rocky shore of Pelham Bay Park, restore coastal habitats, and improve public access to the scenic bay.

Project Update: The project has been awarded to a contractor and has been sent to the Comptroller’s Office for registration.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: October 2016
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: May 2019
Adjusted Completion Date: July 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Pelham Bay Park , Bronx
Along the waterfront between Pelham Bay Landfill and Watt Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project