Pelham Bay Park Natural Shoreline Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will remove intrusive infrastructure from the natural rocky shore of Pelham Bay Park, restore coastal habitats, and improve public access to the scenic bay.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: October 2016
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: May 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Mayoral

Location

Pelham Bay Park , Bronx
Along the waterfront between Pelham Bay Landfill and Watt Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 12/12/2018