Pelham Bay Park Natural Shoreline Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will remove intrusive infrastructure from the natural rocky shore of Pelham Bay Park, restore coastal habitats, and improve public access to the scenic bay.
Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.
Project Timeline
Design
Start Date: September 2015
Projected Completion Date:
October 2016
Completion Date:
August 2018
Procurement
Start Date: August 2018
Projected Completion Date:
May 2019
Completion
Date:
September 2019
Construction
Start Date: September 2019
Projected Completion Date:
September 2020
Completion
Date:
September 2020
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Pelham Bay Park
, Bronx
Along the waterfront between Pelham Bay Landfill and Watt Avenue
Project Staff
Project Liaison: Mike Ortiz
Contact NYC Parks
about this project
Last updated: 07/01/2022