Pelham Bay Park Natural Shoreline Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    63% complete

This project will remove intrusive infrastructure from the natural rocky shore of Pelham Bay Park, restore coastal habitats, and improve public access to the scenic bay.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: October 2016
Completion Date: August 2018

Procurement

Start Date: August 2018
Projected Completion Date: May 2019
Completion Date: September 2019

Construction

Start Date: September 2019
Projected Completion Date: September 2020
Adjusted Completion Date: November 2020

Understand how we build parks.

Funding

Total Funding: $3,214,000
Funding Source: Mayoral

Location

Pelham Bay Park , Bronx
Along the waterfront between Pelham Bay Landfill and Watt Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 08/07/2020