Brooklyn and Queens Reforestation (CNYG-316M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    50% complete

This project includes removal of various invasive species and preparation of all tree pits; furnishing, planting, maintaining and replacing various types of trees in prepared planting tree pits; and installation of native seed mixes in and around areas with existing native species to be preserved; and all work incidental thereto.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: November 2015
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: September 2016

Construction

Start Date: October 2016
Projected Completion Date: April 2019

Understand how we build parks.

Funding

Total Funding: $1,125,000
Funding Source: Mayoral

Location

Various locations in Brooklyn and Queens

Project Staff

Contact NYC Parks about this project

Last updated: 05/24/2018