Citywide Greenstreets Construction

  • Design
    90% complete
  • Procurement
    0% complete
  • Construction
    0% complete

This project will construct greenstreets and green infrastructure elements at citywide locations.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: February 2016
Adjusted Completion Date: December 2017

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Locations

  • Bell Malls , Queens
    Bell Boulevard, 48 Avenue to Horace Harding Expressway
  • Elmjack Mall , Queens
    75th Street, 37th Avenue and Roosevelt Avenue
  • DOT (Non-Parks) Property in Brooklyn
  • DOT (Non-Parks) Property in Manhattan
  • DOT (Non-Parks) Property in Queens
 

Project Staff

Contact NYC Parks about this project

Last updated: 10/15/2018