Citywide Greenstreets Construction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will construct greenstreets and green infrastructure elements at citywide locations.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: February 2016
Completion Date: November 2017

Procurement

Start Date: November 2017
Projected Completion Date: August 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Locations

  • Bell Malls , Queens
    Bell Boulevard, 48 Avenue to Horace Harding Expressway
  • Elmjack Mall , Queens
    75th Street, 37th Avenue and Roosevelt Avenue
  • DOT (Non-Parks) Property in Brooklyn
  • DOT (Non-Parks) Property in Manhattan
  • DOT (Non-Parks) Property in Queens
 

Project Staff

Contact NYC Parks about this project

Last updated: 08/15/2018