Citywide Greenstreets Construction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will construct greenstreets and green infrastructure elements at citywide locations.

Project Update: The project is currently in legal review by staff members at Parks and the New York City Corporation Counsel.

Project Timeline

Design

Start Date: September 2015
Projected Completion Date: February 2016
Completion Date: December 2018

Procurement

Start Date: December 2018
Projected Completion Date: September 2019

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Locations

  • Bell Malls , Queens
    Bell Boulevard, 48 Avenue to Horace Harding Expressway
  • Elmjack Mall , Queens
    75th Street, 37th Avenue and Roosevelt Avenue
  • DOT (Non-Parks) Property in Queens
 

Project Staff

Contact NYC Parks about this project

Last updated: 01/19/2019