McDonald Playground Reconstruction
-
100% complete
-
100% complete
-
21% complete
This project will reconstruct the play area in McDonald Playground.
Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.
Project Timeline
Design
Start Date: August 2017
Projected Completion Date:
August 2018
Completion Date:
April 2020
Procurement
Start Date: April 2020
Projected Completion Date:
December 2020
Completion
Date:
March 2022
Construction
Start Date: April 2022
Projected Completion Date:
April 2023