McDonald Playground Reconstruction

  • Design
    100% complete
  • Procurement
    5% complete
  • Construction
    0% complete

This project will reconstruct the play area in McDonald Playground.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: August 2017
Projected Completion Date: August 2018
Completion Date: April 2020

Procurement

Start Date: April 2020
Projected Completion Date: December 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • Borough President
  • City Council

Location

McDonald Playground , Brooklyn
McDonald Avenue between Avenue S and Avenue T

 