McDonald Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    21% complete

This project will reconstruct the play area in McDonald Playground.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: This project is delayed because it is in the City's best interest to reject all bids received and to resolicit bids.

Project Timeline

Design

Start Date: August 2017
Projected Completion Date: August 2018
Completion Date: April 2020

Procurement

Start Date: April 2020
Projected Completion Date: December 2020
Completion Date: March 2022

Construction

Start Date: April 2022
Projected Completion Date: April 2023

Understand how we build parks.

Funding

Total Funding: $3,614,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Location

McDonald Playground , Brooklyn
McDonald Avenue between Avenue S and Avenue T

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 07/01/2022