Inwood Hill Nature Center Post-Sandy Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the Inwood Hill Nature Center at Inwood Hill Park due to damage caused by Hurricane Sandy.

Due to COVID related impacts, this project may experience schedule delays. We will update the capital tracker as more information becomes available.

Project Update: The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

Project Timeline

Design

Start Date: February 2016
Projected Completion Date: February 2017
Completion Date: July 2019

Procurement

Start Date: July 2019
Projected Completion Date: April 2020
Adjusted Completion Date: September 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • City Council
  • Federal

Location

Inwood Hill Park , Manhattan
West 218th Street west of Indian Road

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 08/07/2020