Inwood Hill Nature Center Post-Sandy Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct the Inwood Hill Nature Center at Inwood Hill Park due to damage caused by Hurricane Sandy.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: February 2016
Projected Completion Date: February 2017
Completion Date: July 2019

Procurement

Start Date: July 2019
Projected Completion Date: April 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • City Council
  • Federal

Location

Inwood Hill Park , Manhattan
West 218th Street west of Indian Road

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/24/2020