Inwood Hill Nature Center Post-Sandy Reconstruction

  • Design
    100% complete
  • Procurement
    40% complete
  • Construction
    0% complete

This project will reconstruct the Inwood Hill Nature Center at Inwood Hill Park due to damage caused by Hurricane Sandy.

Project Update: The solicitation documents have been issued to contractors, and Parks is awaiting the submission of bids.

We are currently soliciting bids for this project. If you are interested in submitting a bid on this project, you can find the documents on our Bid Solicitations page.

Project Timeline

Design

Start Date: February 2016
Projected Completion Date: February 2017
Completion Date: July 2019

Procurement

Start Date: July 2019
Projected Completion Date: April 2020

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:
  • Mayoral
  • City Council
  • Federal

Location

Inwood Hill Park , Manhattan
West 218th Street west of Indian Road

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 12/13/2019