Juniper Valley Park Track and Field Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    14% complete

This project will reconstruct the running track and synthetic turf field and construct an adult fitness area at Juniper Valley Park.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: October 2018

Procurement

Start Date: October 2018
Projected Completion Date: July 2019
Completion Date: March 2021

Construction

Start Date: April 2021
Projected Completion Date: April 2022

Understand how we build parks.

Funding

Total Funding: $5,259,000
Funding Source: City Council

Location

Juniper Valley Park , Queens
Lutheran Avenue between Juniper Boulevard South and Juniper Boulevard North

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 12/04/2021

Was this information helpful?