Nostrand Playground Sport Courts Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    0% complete

This project will reconstruct the basketball courts at Nostrand Playground.

Project Update: The contract is registered.

Project Timeline

Design

Start Date: May 2016
Projected Completion Date: May 2017
Completion Date: November 2017

Procurement

Start Date: November 2017
Projected Completion Date: August 2018
Completion Date: July 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $1 million and $3 million