Rosemary's Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the playground and spray shower at Rosemary's Playground.
Project Timeline
Design
Start Date: March 2017
Projected Completion Date:
March 2018
Completion Date:
April 2018
Procurement
Start Date: April 2018
Projected Completion Date:
January 2019
Completion
Date:
May 2019
Construction
Start Date: June 2019
Projected Completion Date:
June 2020
Completion
Date:
February 2020
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Location
Rosemary's Playground
, Queens
Woodward Avenue between Madison Street and Woodbine Street
Project Staff
Project Liaison: Mike Dockett
Contact NYC Parks
about this project
Last updated: 07/01/2022