Rosemary's Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the playground and spray shower at Rosemary's Playground.

Project Timeline

Design

Start Date: March 2017
Projected Completion Date: March 2018
Completion Date: April 2018

Procurement

Start Date: April 2018
Projected Completion Date: January 2019
Completion Date: May 2019

Construction

Start Date: June 2019
Projected Completion Date: June 2020
Completion Date: February 2020

Understand how we build parks.

Funding

Total Funding: $3,200,000
Funding Sources:
  • Borough President
  • City Council

Location

Rosemary's Playground , Queens
Woodward Avenue between Madison Street and Woodbine Street

 

Project Staff

Project Liaison: Joanne Amagrande
Contact NYC Parks about this project

Last updated: 02/24/2020