Black Rock Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    1% complete

This project will reconstruct the playground at Black Rock Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: March 2016
Projected Completion Date: March 2017
Completion Date: April 2017

Procurement

Start Date: April 2017
Projected Completion Date: December 2017
Completion Date: February 2018

Construction

Start Date: March 2018
Projected Completion Date: March 2019

Understand how we build parks.

Funding

Total Funding: $1,497,000
Funding Source: Mayoral

Location

Black Rock Playground , Bronx
Watson Avenue, Black Rock Avenue between Virginia Avenue and Pugsley Avenue

 

Project Staff

Project Liaison: Michelle Martell
Contact NYC Parks about this project

Last updated: 05/24/2018