Lafayette Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    32% complete

This project will reconstruct Lafayette Playground from an asphalt play surface to multiple uses.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: May 2018

Construction

Start Date: May 2018
Projected Completion Date: August 2019

Understand how we build parks.

Funding

Total Funding: $3,589,000
Funding Source: Mayoral

Location

Lafayette Playground , Brooklyn
Bounded by three streets, Benson Avenue, Bay 43rd Street, and Stillwell Avenue.

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/18/2018