Lafayette Playground Reconstruction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will reconstruct Lafayette Playground from an asphalt play surface to multiple uses.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Between $3 million and $5 million
Funding Source: Mayoral

Location

Lafayette Playground, Brooklyn
Bounded by three streets, Benson Avenue, Bay 43rd Street, and Stillwell Avenue.

 