Lafayette Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Lafayette Playground.

Project Timeline

Design

Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: June 2017

Procurement

Start Date: June 2017
Projected Completion Date: March 2018
Completion Date: May 2018

Construction

Start Date: May 2018
Projected Completion Date: August 2019
Completion Date: July 2019

Understand how we build parks.

Funding

Total Funding: $4,491,000
Funding Source: Mayoral

Location

Lafayette Playground , Brooklyn
Benson Avenue, Bay 43rd Street, Stillwell Avenue

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 09/25/2020