Bergen Beach Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    6% complete

This project will reconstruct Bergen Beach Playground.

Project Update: This project is in active construction.

Project Timeline

Design

Start Date: March 2016
Projected Completion Date: March 2017
Completion Date: April 2017

Procurement

Start Date: April 2017
Projected Completion Date: December 2017
Completion Date: August 2017

Construction

Start Date: September 2017
Projected Completion Date: September 2018

Understand how we build parks.

Funding

Total Funding: $3,262,000
Funding Source: Mayoral

Location

Bergen Beach Playground, Brooklyn
71st Street between Avenue N and Avenue T, adjacent to P.S.312, in Brooklyn

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/20/2017