Coney Island Greenstreets and Green Infrastructure Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    81% complete

This project will construct green infrastructure to capture storm water at Greenstreets at various locations near Coney Island Beach and Boardwalk.

Project Update: The contract completion date has changed. Some of the common reasons why a completion date has changed are: issues with a contractor, design error or omission, unexpected field conditions, change in the scope of the project, pending approval and registration of change orders and/or inclement weather.

Project Timeline

Design

Start Date: February 2015
Projected Completion Date: February 2016
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: August 2018
Completion Date: August 2019

Construction

Start Date: September 2019
Projected Completion Date: September 2020
Adjusted Completion Date: November 2020

Understand how we build parks.

Funding

Total Funding: $1,281,000
Funding Sources:
  • Mayoral
  • Federal

Location

Between Brighton 1st Street, Neptune Avenue, West End Avenue, and the Coney Island Boardwalk

Project Staff

Contact NYC Parks about this project

Last updated: 09/30/2020