Coney Island Greenstreets and Green Infrastructure Construction

  • Design
    100% complete
  • Procurement
    60% complete
  • Construction
    0% complete

This project will construct green infrastructure to capture storm water at Greenstreets at various locations in Coney Island, Brooklyn.

Project Update: Parks has reviewed bids received for this contract and identified the lowest apparent bidder. Working with external agencies, Parks is now reviewing the bid and the vendor’s qualifications.

Project Timeline

Design

Start Date: February 2015
Projected Completion Date: February 2016
Completion Date: December 2017

Procurement

Start Date: December 2017
Projected Completion Date: August 2018

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Understand how we build parks.

Funding

Total Funding: Less than $1 million
Funding Source: Federal

Location

The area between Brighton 1st Street, Neptune Avenue, West End Avenue, and the Coney Island Boardwalk

Project Staff

Contact NYC Parks about this project

Last updated: 08/10/2018